Milestone 0 Overview

Milestone 0 gets your development environment working, introduces the CoffeeMaker code base, and walks you through the debugging and issue-reporting process you will use for the rest of the semester.

Milestone 0 is completed individually. You will work alongside others in your lab section during the Debugging Workshop — and you should, because you will solve problems faster together — but the work lands in your own repository.

   
Start H Aug 20
Individual deliverables due W Aug 26 @ 5:00 pm
Retrospective due W Aug 26 @ 11:45 pm

Expectations

For the Debugging Workshop, you’re expected to:

  • Work with at least one other person to complete the workshop during lab time.
  • Follow the CSC 326 GitHub Processes

Individually, you’re expected to:

  • Complete the Debugging Workshop tasks in your individual repo
  • Run system tests and create issues for at least two bugs
  • Follow the CSC 326 GitHub Processes
  • Practice Project Management
  • Complete the M0 Retrospective
  • Verify your environment setup and show it in your setup video (submit to Moodle)

The workshop itself is designed to be completed without AI — the three bugs are there for you to hunt down with a debugger, because that skill does not transfer from watching a tool do it. AI is welcome in the independent bug hunt, with limits described there.

Deliverables and Rubric

Independent Technical Deliverables (20 points)

For the Debugging Workshop, you will find, report, and fix three bugs. Ensure for each bug that:

  • there’s an issue associated with the bug
  • the issue has steps for reproducing, isolating, and generalizing the bug
  • the bug is fixed and merged to main
  • all issues are closed

Your individual tasks include:

  • create the development branch
  • create branches for each bug, integrate bug fixes, and merge into development and then main
  • find at least two more bugs (you do NOT need to fix these)
  • create issues that include the steps for reproducing, isolating, and generalizing the bugs

Technical Process (5 points)

You are expected to follow good process with finding and fixing bugs:

  • Create appropriate branches for fixing each bug in the debugging workshop.
  • Merge the bug fix branches into main (after the bugs are fixed, of course)
  • Ensure the commits and pull requests should mention the issues they are associated with fixing

Project Management (5 points)

One of the important skills that you’re learning this semester is related to project management – how do you manage working on complex software. And while the Onboarding Project, CoffeeMaker, is not that large there are other complexities to consider. First, you’re learning a new, existing, buggy code base. Second, you’re learning new technologies. Third, you’ll start working on a team and every additional line of communication adds complexity. Project management skills can help you and your team be successful with the project.

There are lots of things that you have to do for Milestone 0. Do a quick skim of the milestone activities to identify the major tasks (you can also look at the deliverables section above). Identify the tasks that you need to accomplish. Each task should have an internal deadline at least 24 hours before the assignment deadline. The goal is to complete steady work on CSC 326 activities rather than waiting until right before the deadline to complete things.

You may discuss with others the appropriate tasks to include in your project management plan.

You will complete the following project management tasks:

  • Create a task list in your repository’s project-management/tasks-m0.md

A table may be helpful for this. And you’ll likely add/edit/delete tasks as you go through the milestone. You should check that all tasks are complete at the end of the milestone so you know you’re done!

Retrospective (5 points)

Complete retros/retro-m0.md in your individual repository. Reflect on how you used AI (or chose not to) for this milestone and on how you engaged with the milestone process. This will include your own contribution, how you worked with others i your lab (or not), and what you would change next week.

Due at W Aug 26 @ 11:45 pm, after your individual deliverable.