The goal of the Onboarding Project is to introduce you to 1) course technologies, 2) basic software engineering processes (branching and merging), and 3) teaming.
For the Onboarding Project you will be creating a web portal for a coffee maker system. Users can add, edit, and delete recipes; stock the inventory; and purchase coffee. Later, we’ll add some more interesting requirements.

Project Overview
You will be provided a partial implementation of the CoffeeMaker program. The program is missing the edit recipe functionality and is lacking a robust test suite. Additionally, there may be bugs that need to be fixed. You will explore the underlying technologies by implementing and testing the edit recipe functionality, adding tests for the rest of the requirements, and fixing any bugs that you may find along the way. There will be new requirements that will need to be implemented. Some of this will be completed on a team, some will be completed individually.
The CoffeeMaker project follows a layered architecture and the details about the repository layer, service layer, and web layer are provided as a starting point for understanding the architecture and design of CoffeeMaker. Unit, integration, system, and acceptance testing are expected. The following sections of the Onboarding Project provide an overview of the major technologies used and resources (like tutorials and documentation) that will help you as you implement CoffeeMaker.
You will work on the CoffeeMaker project in a small workshop team from your lab section.
Onboarding Project Contents
There are four groups of information and expectations that make up the Onboarding project:
CoffeeMaker Overview
- Requirements for Milestone 0 & Milestone 1
- Requirements for Milestones 2-7
- Architecture & Design
- Backend Design
- CoffeeMaker Testing
Process and Build Expectations - Technical Process
Onboarding Project Workshops - Team and Independent Technical Deliverables
The workshops will be linked in as they are added to the project. The specific tasks for each grade category are described in the Project Tasks & Milestone and Rubric sections, below.
- Setup
- Milestone 0: Milestone 0 Overview
- Milestone 1: Milestone 1 Overview
- Milestone 2: Milestone 2 Overview
- Milestone 3: Milestone 3 Overview
- Milestone 4: Milestone 4 Overview
- Milestone 5: Milestone 5 Overview
- Milestone 6: Milestone 6 Overview
- Milestone 7: Milestone 7 Overview
Team Collaboration
You will be evaluated on your contributions to the team portion of the project. Contributions will be considered by reviewing GitHub and completion of the weekly collaboration survey. The survey will be emailed out before the milestone deadlines. These surveys are aggregated for TAs to review and identify if there are concerns that will be discussed during lab.
Project Tasks & Milestones
The following is an overview of the tasks you will complete for the Onboarding project. See the project pages for details.
The specific tasks that you will complete are still under development and refinement. Details will be added each week as you move to the next milestone. A milestone will start each week in lab and end before the next lab (except for the final deadline).
Each week in lab you will work with your project team to complete a workshop activity. This may extend beyond the lab. You will collaborate with this in a team repository. From there you will integrate the code into your individual project and then complete an independent task. Team Deadlines are earlier than Individual Deadlines because individual activities require the team part to be completed first.
| Milestone | Start Date | Team Deadline | Individual Deadline | Retrospective |
|---|---|---|---|---|
| Milestone 0: OBP Setup + Debugging | H Aug 20 | N/A | W Aug 26 @ 5:00 pm | W Aug 26 @ 11:45 pm |
| Milestone 1: Testing + GitHub Actions | H Aug 27 | M Aug 31 @ 11:45 pm | W Sep 2 @ 5:00 pm | W Sep 2 @ 11:45 pm |
| Milestone 2: Backend Design | H Sep 3 | T Sep 8 @ 11:45 pm | W Sep 9 @ 5:00 pm | W Sep 9 @ 11:45 pm |
| Milestone 3: Frontend Design | H Sep 10 | M Sep 14 @ 11:45 pm | W Sep 16 @ 5:00 pm | W Sep 16 @ 11:45 pm |
| Milestone 4: Backend Implementation + Testing | H Sep 17 | W Sep 23 @ 11:45 pm | M Sep 28 @ 5:00 pm | M Sep 28 @ 11:45 pm |
| Milestone 5: Frontend Implementation + Testing | H Sep 24 | M Oct 5 @ 11:45 pm | W Oct 7 @ 5:00 pm | W Oct 7 @ 11:45 pm |
| Milestone 6: Onboarding Project Deadline | H October 8 | F Oct 9 @ 11:45 pm | S Oct 10 @ 5:00 pm | S Oct 10 @ 11:45 pm |
| Milestone 7: Onboarding Project Reflection | S Oct 10 | N/A | T Oct 13 @ 11:45 pm | T Oct 13 @ 11:45 pm |
Rubric
You will be evaluated on the Technical Deliverables you create, the Technical Process you use to develop the product, how well you Collaborate on the final solution, your team’s Project Management, and your weekly Retrospective. You will also complete two peer evaluations — one at the Milestone 4 team deadline and one at the end of the project — which account for the additional points in Team Collaboration.
Technical Deliverables
Each milestone will have you complete technical tasks. Some will be completed as a team, you will then extend that team work with individual deliverables. Technical deliverables include technical documents like design and tests.
Technical Process
You will follow GitHub technical processes when working on both your team and individual repositories.
Collaboration
You’re expected to contribute to teach team deliverable; your work should be visible in the GitHub repository through commits to a branch that is then PRed into development and main. Additionally, you will reflect on your team’s collaboration each week via the team collaboration surveys (these will be emailed to you).
Project Management
When working with a team, it is important that everyone knows who is supposed to do what. You will maintain project management documentation in your repository — task lists, a communication policy, and an AI policy — and update it through each milestone.
Retrospective
Every milestone ends with a retrospective, worth 5 points, submitted in the retros folder of your individual repository. Reflection is a standard practice in agile processes, and doing it every week — rather than only at the end — is what makes it useful.
Each retrospective covers two things:
- How you used AI, or chose not to, on this milestone’s tasks — what you asked for, what came back, and whether it helped. See Generative AI for how this doubles as your disclosure.
- How you engaged with the milestone process — your own contribution, how your team worked together, and what you would change next week.
Retrospectives are due at 11:45 pm on the day your individual deliverable is due, a few hours after the deliverable itself, so you can reflect on work you have already finished. “I did not use AI on this milestone” is a complete answer for the first half — say what you did instead.
Overall Grade
| Category | Points |
|---|---|
| Team Technical Deliverables | 90 |
| Independent Technical Deliverables | 120 |
| Technical Process | 70 |
| Team Collaboration | 90 |
| Project Management | 40 |
| Retrospective | 40 |
| Total | 450 |
Grades by Milestone
| Milestone | Team Technical Deliverables | Independent Technical Deliverables | Technical Process | Team Collaboration | Project Management | Retrospective |
|---|---|---|---|---|---|---|
| Milestone 0: OBP Setup + Debugging | 0 | 20 | 5 | 0 | 5 | 5 |
| Milestone 1: Testing + GitHub Actions | 10 | 10 | 10 | 5 | 10 | 5 |
| Milestone 2: Backend Design | 10 | 10 | 5 | 5 | 5 | 5 |
| Milestone 3: Frontend Design | 10 | 10 | 5 | 10 | 5 | 5 |
| Milestone 4: Backend Implementation + Testing | 15 | 15 | 20 | 25 | 5 | 5 |
| Milestone 5: Frontend Implementation + Testing | 15 | 15 | 20 | 15 | 5 | 5 |
| Milestone 6: Onboarding Project Deadline | 30 | 30 | 5 | 15 | 5 | 5 |
| Milestone 7: Onboarding Project Reflection | 0 | 10 | 0 | 15 | 0 | 5 |
| Totals | 90 | 120 | 70 | 90 | 40 | 40 |
Deductions
You must contribute to the OBP and to do so, you must demonstrate that your personal development environment is set up and configured properly for development in CSC 326 by either showing a demo on your laptop or providing a video demo of a desktop environment to your TA. Additionally, the teaching staff reserves the right to make deductions for non-participation in class activities. The deduction could lead to a zero on the assignment for significant lack of participation.
| Grade Item | Deduction |
|---|---|
| Development Environment not set up | -50 |
| Participation Deductions | up to -450 |