Updated for Fall 2026
Milestone 4 Overview
Milestone 4 builds the backend you designed in Milestone 2. Entities, repositories, services, controllers, DTOs, mappers, and the tests that prove they work.
Everything before this milestone produced documents. This one produces working software, and it is the first time your design is checked against something that can disagree with it.
- Your team implements UC2 Add Recipe, UC4 Edit Recipe, UC5 Update Inventory, and UC7 Add Ingredients.
- You individually implement UC6 Order Beverage on top of your team’s work.
Implementation and testing take longer than design. Plan accordingly — the points have gone up because the work has.
| Start | H Sep 17 |
| Team deliverables due | W Sep 23 @ 11:45 pm |
| Individual deliverables due | M Sep 28 @ 5:00 pm |
| Retrospective due | M Sep 28 @ 11:45 pm |
Expectations
Each team member is expected to:
- [Individual] Contribute to team work
- [Team] Complete the Backend Implementation Workshop with your team
- [Team] Select a unified design for UC2 and UC4 from your individual Milestone 2 designs
- [Team] Implement and test UC2, UC4, UC5, and UC7, including the team AI implementation activity
- [Team] Complete Peer Evaluation 1 by the team deadline
- [Individual] Integrate the team’s work and implement and test UC6
- [Individual] Complete the AI Defect Injection Activity — find out whether your tests can catch a bug
- [Individual] Complete your Milestone 4 retrospective
- [Team & Individual] Follow the CSC 326 GitHub Processes
Deliverables and Rubric
Team Technical Deliverables (15 points)
- Complete the Backend Implementation Workshop. This is exploratory and stays on its own branch — it is not merged.
- Complete the design selection, recorded in
technical-documents/design-selection-m4.md. - Implement and test the arbitrary ingredient functionality for UC2, UC4, UC5, and UC7, meeting the Done Criteria.
- Complete the AI implementation activity, recorded in
technical-documents/code-review-m4.md.
Design changes made during implementation go in the Implementation Decisions section of technical-documents/backend-design.md, and the design itself gets updated to match what you built. System tests go in technical-documents/system-tests.md — at least two per use case, eight in total, with actual results from Postman.
Independent Technical Deliverables (15 points)
- Integrate your team’s implementation and tests into your individual repository, using appropriate branching and merging.
- Implement and test UC6 Order Beverage, meeting the Done Criteria. At least two system tests for UC6 in
technical-documents/system-tests.md, with results from Postman, and no regression in the team’s functionality. - Complete the AI Defect Injection Activity, recorded in
technical-documents/test-effectiveness-m4.md. - Write
technical-documents/backend-design-reflection.md: reflect on your team and individual backend designs and implementations, what changed during implementation, and how the team’s design of UC2, UC4, UC5, and UC7 shaped your implementation of UC6.
Technical Process (20 points)
You are expected to follow the CSC 326 GitHub Processes and ensure the following:
- At least 60% line coverage and 50% branch coverage. The build reports where you stand rather than failing, so read the number — a green check does not mean you met it.
- Work completed in a branch, one per feature, with an owner
- Pull requests used consistently to merge into
developmentand thenmain(the workshop branch is the exception and is never merged) - A team member other than the author reviews and merges each pull request
- All delivered code merged into
main - Design changes recorded in
technical-documents/backend-design.md
Team Collaboration (25 points)
You are expected to contribute to your team’s implementation. That means we want to see that everyone worked on the milestone, including both technical and non-technical work — commits from each team member, pull request approvals from each team member, and document editing by each team member. The contributions need to be meaningful, and we are looking for roughly equal effort.
If you worked together on a task, note that in your task list. Be ready to discuss it at your check-in next week.
Peer Evaluation 1
Milestone 4 is the first substantial implementation push of the Onboarding Project, so it is also the first checkpoint on how your team is actually working together. Waiting until the end of the project to surface a teaming problem is too late to fix it — this is the point at which the teaching staff can still help.
Fill out the Peer Evaluation 1 Form by the team deadline, W Sep 23 @ 11:45 pm.
You will rate yourself and each of your teammates on a scale of 0 (Never) to 5 (Always) or 6 (Above and Beyond) on the following:
- On-time attendance and contribution to team meetings (including lab time)
- Doing their fair share and completing assignments and responsibilities in a timely manner
- Making useful contributions to the lab assignments (e.g., helps formulate goals, asks for ideas, gives ideas, clarifies ideas, identifies action steps)
- Efficient team procedures (e.g., focuses on reaching agreements, listens carefully, confronts issues, focuses on facts, reduces tension)
- Having a constructive, open-minded, and cooperative attitude toward the team and the project (e.g., encourages feedback on themselves, draws others out, shows enthusiasm, responds positively to others’ ideas)
You will complete a second peer evaluation at the end of the project, in Milestone 7.
Project Management (5 points)
Update your team’s project management documents:
- Record your Milestone 4 tasks, owners, and deadlines in
project-management/tasks-m4.md, and mark them off as they are completed. - Revise your team’s communication and AI policies in
project-management/index.mdif your retrospective surfaced something that needs to change. This is the milestone where AI can write code that ships with tests behind it, so your policy needs to say who reviews generated code and how it is disclosed in a pull request.
Retrospective (5 points)
Complete retros/retro-m4.md in your individual repository. See the Retrospective overview for what is expected.
In addition to the usual reflection, Milestone 4 asks you one specific question:
Which injected bug escaped your tests, and what does that tell you about the rest of your suite?
Due at M Sep 28 @ 11:45 pm, after your individual deliverable.